Answered: Is there an adjudicator’s contract in the NEC4 family?

There is, however the NEC3 Adjudicator’s Contract has been changed so that it can be used for the appointment of board members to a Dispute Avoidance Board under option W3 and has been renamed the...

View Article


Answered: Does NEC4 provide for consensual dispute resolution?

Consensual dispute resolution has become more popular over recent years and including this in NEC3 contracts was a popular Z clause. NEC4 includes a four week period for escalation and negotiation of a...

View Article


Answered: Can you procure a design and build contract using the NEC4...

Yes, and there is a new secondary option for Contractor’s design which provides more extensive provisions for design and build contracting.

View Article

Answered: Does the NEC4 Supply Contract (SC) include a Schedule of Cost...

Yes, this addition to the Supply Contract brings much greater clarity to the definition of Defined Cost.

View Article

Answered: Does the NEC4 Term Service Contract (TSC) include a Schedule of...

Yes, this addition to the Term Service Contract brings much greater clarity to the definition of Defined Cost.

View Article


Answered: Does the NEC4 Professional Services Contract (PSC) include a...

Yes, this addition to the Professional Services Contract brings much greater clarity to the definition of Defined Cost.

View Article

Answered: Is value engineering included in NEC4?

It is, however the NEC4 calls this Contractor’s proposals. The Contractor can make a proposals that reduce cost which if accepted by the Project Manager the Contractor shares in the cost savings.

View Article

Answered: What would I use the NEC4 Design Build Operate Contract (DBO) for?

Design, build and operate is a procurement method that integrates design, construction, operation and / or maintenance activities. This gives clients a more integrated, whole life solution for...

View Article


Answered: Does the NEC4 encourage making decisions about assets based on...

Yes, there is a new secondary option which incentivises the Contractor to make proposals to reduce the cost of an asset over its whole life.

View Article


Answered: What would I use the NEC4 Alliance Contract (ALC) for?

Alliancing has grown in popularity over the last 10 years or so. It involves the integration of delivery teams for large, complex projects or programmes. The client only need enter into a single...

View Article

Answered: Can you procure an alliance contract under NEC4?

Yes, there is a new form of contract specifically for this, the Alliance Contract (ALC), it is initially being published as a consultative form, presumably so that NEC can receive feedback from...

View Article

Answered: Can you procure a design, build and operate contract under NEC4?

Yes, there is a new form of contract specifically for this, the Design, Build Operate (DBO) Contract.

View Article

Answered: Can I still use NEC3 for my contracts after NEC4 is published?

Yes, it is up to you to decide whether or not you want to adopt NEC4 for your contracts. In the short term you may choose to stick with NEC3 until you’ve had chance to understand what the differences...

View Article


Answered: Can you summarise the key differences between NEC3 and NEC4?

The following is an extract from Glenn Hide's website. "The new NEC4 suite of contracts are being published on the 22nd June this year. Below is a summary of some if the main changes, in terms of the...

View Article

NEC ECC: Collaborative working/mutual trust & co-operation

There is a fully integrated team between the Employer & the Contractor. The Contract is Option "C" but pain/gain & target was removed, without LD's and includes a fixed fee payable on milestone...

View Article


NEC ECC: Advice for using Specification for Highway Works

When using the Specification for Highway Works (SHW) with NEC3 ECC, what is the best way to structure the contract documents to ensure clarity and avoid ambiguity? My concern is that whilst the NEC has...

View Article

Answered: Sub-Contract Fee Under Option B

What matters is your 'direct fee percentage' as entered in your contract's Contract Data. That is the deal which is struck under NEC option B and you have signed up for it at 0%. Consequently, for the...

View Article


Answered: Payless notices for CEs yet to be agreed

As I understand it, if you, as a Subcontractor, have applied for these amounts, then the Contractor would have to issue a Payless Notice stating why you are not (yet) entitled to them i.e. they have...

View Article

Answered: NEC ECC: Compensation event due to changes in works information...

I think : - the compulsory site briefing is contractually irrelevant; - this comes down to what exactly was said in the Works Information in terms of constraints that the Contractor has to work under....

View Article

Answered: NEC ECC: Defects in relation to programme

I think it is a good idea to show them on the programme. We could debate for a while whether they have to be or not, but it will just be quicker to do it rather than argue whether they should be there...

View Article