Quantcast
Channel: ReachBack by BuiltIntelligence - Recent questions and answers
Viewing all articles
Browse latest Browse all 3438

Answered: Payless notices for CEs yet to be agreed

$
0
0
As I understand it, if you, as a Subcontractor, have applied for these amounts, then the Contractor would have to issue a Payless Notice stating why you are not (yet) entitled to them i.e. they have not been agreed / contractually implemented.

Viewing all articles
Browse latest Browse all 3438

Trending Articles