Quantcast
Channel: ReachBack by BuiltIntelligence - Recent questions and answers
Browsing all 3438 articles
Browse latest View live
↧

Answered: NEC ECC: Could the PM while making his own assessment have made...

Not really, but he could evaluate what he believes the compensation event should have been in accordance with the contract. These are not subject to a revisit after implemented - only through...

View Article


NEC ECS: Are there specified reasons in the contract for removing a...

Z1.12.4: 24.2 - The Contractor may, having stated his reasons, instruct the Subcontractor to remove any person under his control. The Subcontractor then arranges that, after one day, such person has no...

View Article


NEC3 ECC: Process for correcting defects and accepting subcontractors

A small area of new pavement construction has settled and is beginning to crack. This occurs before completion of the works in ECC option A (Employer -designed contract). What do the Supervisor and...

View Article

NEC3 ECC: Recoverable cost of Subcontractor is rejected?

The Contractor says that if the Project Manager objects to XYZ Ltd he would incur additional costs which he would seek to recover as a compensation event.  How should the project manager respond?

View Article

Answered: NEC ECS: Are there specified reasons in the contract for removing a...

The Contractor can instruct this, but it is intended to be for matters such as health and safety breaches, security or disorderly behavior. If it was for any other reason then the Subcontractor could...

View Article


Answered: NEC ECC: PM assumptions

Yes, the PM could not contractually do anything else! They can make their own assessment of the assumptions, and practically speaking should present these in a detailed format so the Contractor can...

View Article

NEC ECC: Option A Subcontractor fee percentage

NEC Option A - Activity schedule. We have received a quote which the subcontractor has applied fees which are higher than the tendered fees submitted by the main contractor. Ie they have applied a 20%...

View Article

NEC ECC: In the contract what is the definition of Defined Costs

When reading the shorter schedule of cost components, what is the definition of defined costs that you should be reading in conjunction with?

View Article


Answered: NEC ECC: What are disallowed costs when it comes to option A?

A very good question. A few Employers seem to do the same thing and my question is exactly the same as yours! The simple answer is there is no such thing under option A and you only have disallowed...

View Article


Answered: NEC ECC: Option B, where a item of work is reduced, can we claim...

If the item of work has been reduced due to a change in the Works Information then that would be a compensation event which, unless otherwise agreed, would be assessed as the Defined Cost + fee that...

View Article

NEC ECC: Defects in relation to programme

Further to a previous question which centered on the PM instructing the Supervisor to raise incomplete works as Defects. We would be grateful for your view on the following; 1. The incomplete works...

View Article

Answered: NEC ECC: Interest due to the Employer from overpayment to the...

Clause 51.3 deals with interest on corrected amounts. The clause is silent on which party pays therefore can be either party. In the context of the second bullet point this makes sense as adjudication...

View Article

Answered: When will NEC4 be available?

The new contracts will be available in June 2017, keep checking www.neccontract.com for more information on this.

View Article


Answered: Will NEC4 automatically apply to my NEC3 contracts?

No, if you have a contract that is currently based on an NEC3 contract this will continue to be the case after NEC4 is published. NEC4 will only apply to contracts drafted after NEC4 is published, and...

View Article

Answered: How does NEC4 deal with a Project Manager not replying the...

Good question, for many years people (contractors?) have campaigned for deemed acceptance of the programme in the same way that a compensation event notification and quotation can become deemed...

View Article


Answered: Are Working Area Overhead and / or People Overhead included in NEC4...

No, NEC have abandoned use of these concepts as users of the contract have reported many issues with interpretation of them over the years. Instead, costs that would have been covered by the...

View Article

Answered: How does NEC4 improve on NEC3 in terms of auditing Defined Cost?

The NEC4 cost-based contracts, i.e. main options C, D, E and F include a procedure for the Contractor to instigate a review and acceptance of its Defined Cost by the Project Manager. This new procedure...

View Article


Answered: How does NEC4 provide for Building Information Modelling (BIM)?

A new secondary option has been included in the NEC3 Engineering and Construction Contract (ECC) to support the production of information for BIM. Under this option the Contractor provides an...

View Article

Answered: How does NEC4 provide for Building Information Modelling (BIM)?

A new secondary option has been included in the NEC3 Engineering and Construction Contract (ECC) to support the production of information for BIM. Under this option the Contractor provides an...

View Article

Answered: Does the Contractor have to submit an application for payment under...

Under the NEC3 Engineering and Construction Contract (ECC), the Project Manager has an obligation to assess amounts due to the Contractor regardless as to whether the Contractor has submitted an...

View Article
Browsing all 3438 articles
Browse latest View live