Quantcast
Channel: ReachBack by BuiltIntelligence - Recent questions and answers
Browsing all 3438 articles
Browse latest View live

NEC ECC: Contractor's liability for delay due to change in specification...

It was suggested that a brick test be constructed to a similar project nearby however no date was given of when this should be complete and we assumed prior to commencement of the brickwork would...

View Article


Answered: NEC ECC: Contractor's liability for delay due to change in...

It looks like the last action was your submitted CEQ (which I assume included an assessment of time) was not accepted by the PM and it looks like he has made a PM's quotation assessment which you do...

View Article


Answered: NEC ECC: Does Contractor have to follow an instruction after...

This question has been asked previously, see link below;http://reachback.builtintelligence.com/12949/additional-instruction-completion-potential-disadvantages Notwithstanding the time issues, as...

View Article

Answered: NEC ECC: Ownership of the weather risk and commercial opportunity

Without details of the amendment, I cannot give a meaningful / considered comment on whether the Employer or Contractor owns the weather - or to be more precise, to what extent and which weather...

View Article

Answered: NEC TSC: How does Contractor go about changing a main subcontractor...

You can do this, but it would be by either : - when the Subcontractor's subcontract term finishes i.e. the the end of the 'service period'; or - via the termination procedures of the contract : this...

View Article


Answered: NEC ECC: Option B - Can a Compensation Event be added to the Scope...

The Project Manager can instruct a change to the 'Works Information' (under NEC3) / 'Scope' (under NEC4) and this is a compensation event under clause 60.1(1). So, how can I say this in the nicest...

View Article

FIDIC: The Employer declare that All information relating the site, soil data...

If so, as a Contractor, shall we conduct construction work with confidence? It means Any subsequent damage caused by the incorrect info provided by the employer must be beared by the contractor?

View Article

Answered: NEC ECC: Is lack of information in the Works Information a...

The Works Information is provided by the Employer.  If it says to 'do something' then that is what you price for in the Activity Schedule.  If the 'something' subsequently changes to 'something else...

View Article


Answered: NEC ECC: Works Information identifies "working days" - would this...

The argument here is tenuous to say the least. In secondary Option  X7: delay damages at clause X7.1 it uses the words "for each day" and not the words "for each Working Day". Therefore there's no...

View Article


Answered: NEC ECC: Option C - Instructing works without agreed prices.

No this is not allowed under the contract. the bit that is correct is that the works can proceed without first agreeing the quotation. However, the compensation event should be assessed as a reasonable...

View Article

Answered: NEC ECC: Weekend working to mitigate delay

There are two options here. Either the Contractor assesses the compensation event based upon a five day week and then sees/agrees the impact on planned Completion and thus Completion Date accordingly....

View Article

NEC ECS: Wrongful termination by the Contractor

If a Contractor terminates the contract through the use of R11 without notifying the Sub-Contractor of any defaults, is this a wrongful termination? In addition to this, after termination, if the...

View Article

Answered: NEC ECC: Defects Date

The Supervisor is obliged to issue the Defects Certificate either at; - the defects date,   or - the end of the last defects correction period, if a later date. Any outstanding contract administration...

View Article


NEC ECC: Works Information identifies "working days" - would this apply to...

The NEC3 does not give a definition of 'day'; however in one contract there is a separate definition given for 'Working Day' which specifically excludes weekends and Bank Holidays. In a delay situation...

View Article

Answered: NEC ECS: Wrongful termination by the Contractor

Well, putting myself in the Contractor's position it would substantially help if they had informed you of how exactly you were in default / substantially failing to comply with your obligations, as you...

View Article


NEC:ECC option A how do I assess compensation Events when the SSCC does not...

Contractor wants to extend Working Area to include factory so can assess manufactured items using SSCC method to calculate people & equipment, but it is difficult to use this method to assess...

View Article

Answered: NEC ECC: Employer drafting and accepting Contractors's programmes

This is not unheard of - but more common at Contractor/Subcontractor level. First question would be why have you given a job to a Contractor who has an inability to produce a programme? It is not...

View Article


Answered: NEC ECC: Direct fee and subcontract fee on NEC3 ECC option E contract

No, these three make up Defined Cost and are intended to avoid the need for the calculation of minutae when compensation events occur, so - the percentage adjustment for listed Equipment is normally a...

View Article

Answered: NEC:ECC option A how do I assess compensation Events when the SSCC...

Before any decision is made on whether to extend the Working Areas have a look at NEC3 ECC clause 15.1 which gives two reasons for not accepting a proposed addition to the Working Areas. From a purely...

View Article

Answered: NEC ECSC: Does the Price List form part of the Works Information...

The answer is 'No'. However, when the Price List is written by the Employer, it is not unusual for there to be a reference to the Price List from the Works Information incoporating the descriptions in...

View Article
Browsing all 3438 articles
Browse latest View live