NEC ECS: Wrongful termination by the Contractor

$
0
0
If a Contractor terminates the contract through the use of R11 without notifying the Sub-Contractor of any defaults, is this a wrongful termination? In addition to this, after termination, if the Contractor/Project Manager fails to certify a payment within 14 weeks what happens next?