Answered: NEC ECS: Option A Compensation Event Assessment

Firstly, the Contractor should show the effects of the compensation event and show its effects (if any) on the "planned Completion" milestone. If this effect is agreed, the amount that planned...

View Article


NEC ECS: Option B - Does PWDD include value of unimplemented Compensation...

Am I correct in stating that the "estimated" cost of unimplemented  compensation events should not be included in a Contractors' assessment of the amount due to the subcontractor? The PWDD under...

View Article


Answered: NEC ECS: Option B - Does PWDD include value of unimplemented...

Yes that is correct. The PWDD relates to work completed in the BoQ. A compensation event assesses changes to the Prices (63.1) Assessments for changed Prices are in the form of changes to the BoQ...

View Article

Answered: NEC ECC: Option X5 and X7 - Sectional Completion

No - the rules around Sectional Completion are the same as Completion Date i.e. only agreed acceleration can ever bring forward a sectional Completion Date and an implemented compensation event move it...

View Article

Answered: NEC ECC: Option A correct fee % application

Firstly, I am a little confused when you say "a required 3rd tier company" which implies they are a Subsubcontractor. However, I will proceed as if they are a Subcontractor - correct me if wrong. Go...

View Article


NEC ECSC: Design liability under Short Subcontract

We are engaging a scaffolding company under the short subcontract for assembly and hire of temporary works, the design of which has been let under a separate purchase order with different T&C's....

View Article

Answered: NEC ECC: Option A- Accepting subcontractors

Appointing a Subcontractor without prior acceptance is not a Defect as it's not "a part of the works not in accordance with the Works Information" as required by clause 11.2(5). If the base course is...

View Article

Answered: NEC ECC: Option A - Zero Defects

Michael is absolutely correct here, Completion should not have been certified with 4000 Defects and the PM is in breach of contract for doing so. Maybe the Employer should consider recovering their...

View Article


NEC ECC: Option A - Clause 34.1, who pays for the management costs during the...

We are under a NEC3 ECC Contract Option A - The Employer has issued a stop notice under Clause 34.1 and referred to it as a De-scope. He has 13 weeks to advise us to re-start the works. Who pays for...

View Article


NEC ECC: Do I have to credit management charges for cancelled scope due to...

The Employer cannot provide access to site, so to mitigate his liability, he has decided to Terminate the Contract. He is now asking for a credit for the works that would now not be installed, and also...

View Article

NEC3 ECS: Option C - Compensation Event for a client delay

Event has occurred under NEC3 ECS Main Option C. An event had occurred during the construction phase of the project, which stopped all works for approximately 10 months before the works resumed. It was...

View Article

Answered: NEC ECC: Do I have to credit management charges for cancelled scope...

The standard termination provisions are set out in Section 9. From your comments it appears that the Employer has terminated for a reason other than R1 to R21. Was this stated on the termination...

View Article

Answered: NEC3 ECS: Option C - Compensation Event for a client delay

Would have been better if the Subcontractor had been given Contractor assumptions on which to base their quotation and allowing a forecast (and if necessary a series of forecasts as time moves on). It...

View Article


Answered: NEC ECS: Option b subcontract %

In answer to your questions : (1) Should contract data part 2 not include a section for pricing people rates? Yes, or at the very least a reference to a schedule where they are contained. You could...

View Article

NEC3 ECS: Option C - Compensation Event for a client delay

Event has occurred under NEC3 ECS Main Option C. An event had occurred during the construction phase of the project, which stopped all works for approximately 10 months before the works resumed. It was...

View Article


Answered: NEC ECC: If the Project Manager accepts a Project programme and the...

Contract obligates that a Contractor shows a planned Completion milestone and a Completion Date milestone. If a Contractor is showing planned Completion beyond Completion Date, it means they are...

View Article

Answered: NEC ECC: Option A - Activity Schedule: Can a Client ask a...

No there is no where in the contract that expressly allows them to insist you change your activity schedule. The Contractor can propose to revise it under 54.2 and the Project Manager has to accept/not...

View Article


Answered: NEC ECC: Option A - Clause 34.1, who pays for the management costs...

You haven't explained why the de-scope is happening which does have a bearing on the answer, non-the-less the clause 34.1 instruction is a compensation event under clause 60.1(4) unless the reason for...

View Article

NEC ECS: Is main Contractor contracharge against a Subcontractor's CE on...

As a subcontractor working under NEC3 subcontract we were asked to provide a quote to get a previously approved specialist supplier to carry out works as a CE to our main subcontract which our main...

View Article

Answered: NEC TSC: Service Manager ability to remove an employee under Option A?

For a legal definition of an employee, you would need to take advice outside of this group. The removal can be done for whatever reason the Service Manager wants providing he or she states the reason...

View Article