Quantcast
Channel: ReachBack by BuiltIntelligence - Recent questions and answers
Viewing all articles
Browse latest Browse all 3438

NEC3 ECSC: Change in a Completion Date

$
0
0
Under the short form, the PM has notified C of a CE due to change of WI. PM has requested quotation. I have quoted with a 1 day time delay to Completion Date, If I bring in an additional squad to carry out the work relating to the CE and the squad that is stated in the resource schedule on accepted programme carry on with their programmed work, am I still entitled to the 1 day time delay?

Viewing all articles
Browse latest Browse all 3438

Trending Articles