Answered: NEC3 ECC Option B Cl60.4 CE on total quantity

$
0
0
The first bullet point makes it clear that a difference which arises from a change to the Works Information is always a compensation event. If this is the case then we are left with two tests which must both be satisfied. The last bullet aims to act as a cut off for small items.