Answered: NEC3 ECC: Time frame for assessing Compensation Events when requesting more information

$
0
0
Project Manager should respond to your quotation (or additional information) within two weeks. If they fail to do so you can/should notify them of this lack of response. A further two weeks later with no response would mean that your quotation has been "deemed" accepted. If they say they are making their own assessment and don't, then another reminder followed by a further two weeks of silence would also mean original quote is deemed accepted.