FIDIC: Admeasurement Contract Risks in FIDIC MDB 2010

$
0
0
FIDIC MDB 2010 - For Works Designed by Employer and Constructed by Contractor

Re-measurable / Admeasurement Type of Contract

1) If the quantities increase (reference is Tender BOQ) during the execution of project, does this can be claimed for EOT?
2) For items, shown in Drawing but missed in Tender BOQ - Can contractor claim for variation during the execution of works?
3) Does the rate changes for any boq item, if the quantity is more than 25% of Tender BOQ?
4) Who is responsible if all the items in the Tender drawings are not reflected or missed by the Employer in the Tender BOQ?