The definition of Works Information 11.2(19) is information which either
- specifies and describes the works or
- states any constraints on how the Contractor Provides the Works
In this instance because the quantities are stated in the Works Information then a change in quantity is a change to the Works Information and the Contractor can notify a compensation event under clause 60.1.1 change to the Works Information.
The usual rule is that in ECC main Option A and C the Contractor takes the risk for the quantity of work required. However if quantities are stated in the Works Information and these are incorrect then this is a change in the Works Information and a compensation event under clause 60.1(1)
I would agree with your comment that if quantities are stated in the Works Information and these are incorrect then this is an Employer risk.
So if I were the Contractor I would notify a compensation event under 60.1(1) for a change in the Works Information.
- specifies and describes the works or
- states any constraints on how the Contractor Provides the Works
In this instance because the quantities are stated in the Works Information then a change in quantity is a change to the Works Information and the Contractor can notify a compensation event under clause 60.1.1 change to the Works Information.
The usual rule is that in ECC main Option A and C the Contractor takes the risk for the quantity of work required. However if quantities are stated in the Works Information and these are incorrect then this is a change in the Works Information and a compensation event under clause 60.1(1)
I would agree with your comment that if quantities are stated in the Works Information and these are incorrect then this is an Employer risk.
So if I were the Contractor I would notify a compensation event under 60.1(1) for a change in the Works Information.